Yorkshire Water has revealed work is going on in the Crimple Valley in Harrogate to fix sewage problems

Yorkshire Water has revealed it is beginning the next phase of its upgrade to wastewater infrastructure in and around Pannal in Harrogate in support of new housing developments in the area.

Contract partners, Mott MacDonald Bentley, are already underway with constructing a wastewater pumping station at Harlow Carr Gardens, a storage tank at Fulwith Mill Lane, and 5km of new sewer pipework around the area, with work currently taking place on Lady Lane.

The next stage will see construction begin on a second pumping station and second storage tank, to build further pressure relief and capacity into the network.

Construction of the pumping station has begun off Spring Lane and is expected to be completed in February 2027.

Harrogate resident Ann Morris took this photograph of work being carried out on behalf of Yorkshire Water near Fulwith Lane in Harrogate to tackle sewage problems. (Picture contributed)

The site will be accessed via an entrance that will be built opposite the junction of Spring Lane and Westminster Drive, and to keep everyone safe, there will be temporary traffic lights in place while the entrance is constructed.

The second storage tank will be built behind Pannal Green, where preliminary works have started.

Together, the storage tanks will build over 2000m3 of extra capacity into the existing network, holding up to two million litres of excess wastewater and rainwater, in support of new developments.

Pamela Ajayi, project manager at Yorkshire Water, said: "We’re making good progress with the project, which is incredibly important for the Harrogate area’s resilience as it grows

"As we continue, we’ll keep doing everything we can to minimise disruption.

"Thank you to everyone for their ongoing patience and understanding.”

The work in Harrogate forms part of Yorkshire Water’s £8.3bn improvement programme – its largest ever investment in to infrastructure, customer experience, and environment.

Planning permissions are already in place for more than 2,000 new dwellings in South West Harrogate that will be delivered over the next 12 years, some of which are already being progressed.

After years of public criticism from local politicians, campaigners and residents over alarming levels of pollution and water quality in Harrogate and North Yorkshire, Yorkshire Water says the results of its record investment are starting to be seen in the Harrogate district.